1. Once the finished
elevation of concrete has been determined with a laser or string
line, position a 12" to 16" length of EMT conduit
on the subgrade at the strikeoff point. The length of conduit
may vary due to depth of concrete and/or condition and type
of subgrade. Sand may require 2' or more.
|
|
|
|
2. Insert the AccuScreed
Driver into the conduit. Using a soft faced or a Dead Blow Hammer,
strike the top of the Driver until the height marker aligns
with the laser or string line.
|
|
|
|
3. Remove the Driver
and insert the AccuScreed Yoke into the conduit. Regardless
of the angle of cut or the degree of rotation, the Yoke will
maintain the exact position as indicated by the height marker.
Repeat this same procedure for each screed location.
|
|
|
|
4. Set the 1-1/4"
ID,1-5/8" OD screed pipe on top of the Yoke and you are
ready to pour. The top of the screed pipe will precisely match
the strikeoff point! It's simple, fast and convenient!
|
|